Roles and Activities > Manager Role Set > Project Manager > Prepare for Phase Close-Out

Workflow Details:

The end of a phase represents a point of synchronization (of technical and management expectations) and closure for a project, and it coincides (more or less) with the end of an iteration. However, unlike other iterations, the iteration that terminates a phase should leave few loose ends and issues to be carried forward into the next iteration (which will be in the next phase). Indeed, phase ends mark a point at which it is possible to consider re-scoping and even re-contracting a project. For example, the inception phase is exploratory and may be appropriately performed under a time-and-materials or cost-plus type of contract. The elaboration phase could be done as a fixed-price or cost-plus contract, depending on the degree of novelty of the development. Enough is known about the system by the construction and transition phases that fixed-price contracts are more appealing to acquirer and vendor.

The phase end is marked by a major milestone, at which a Lifecycle Milestone Review is conducted. This is intended to achieve concurrence among all stakeholders on the current state of the project. These reviews are usually formal and are conducted with some ceremony, to demonstrate to all stakeholders that the aims of the phase were achieved. The end of the transition phase is marked by the Product Release Milestone and the associated Project Acceptance Review. The phase-end actions for the transition phase are covered in Activity: Prepare for Project Close-Out.

The Project Manager will have planned, going into the final iteration of the phase, to have all required artifacts ready for the Lifecycle Milestone Review. However, there will still be an Activity: Assess Iteration and an Activity: Iteration Acceptance Review before the Lifecycle Milestone Review is held. If the iteration has gone well, there will be little to do in this activity (Prepare for Phase Close-Out) other than distributing phase-end artifacts to stakeholders. The project manager may decide that certain issues arising from the Iteration Assessment or issues remaining in the Issues List need to be addressed before the Lifecycle Milestone review, and cannot carried over into the next phase. This means that, in effect, a micro-iteration will occur, in which selected problems will be fixed and issues resolved, although in terms of workflow, this can be considered an extension of the final iteration.

Check Status of Required Artifacts To top of page

The Project Manager will check each of the artifacts required for the phase end, using information from the latest Iteration Assessment and Status Assessment. Where there are open issues or problems that the Project Manager believes would prevent a successful Lifecycle Milestone Review, work is initiated to resolve them, before the artifacts are distributed to the stakeholders.

Artifacts Required

Schedule Configuration Audits To top of page

If required, the Project Manager arranges for functional and physical configuration audits to be conducted according to Perform Configuration Audit.

Conduct a Phase Post-Mortem Review To top of page

Once any activities triggered by Check Status of Required Artifacts have been completed, the Iteration Assessment can be amended to reflect the improved state. A post-mortem review is then held to determine whether the project is ready for the Lifecycle Milestone Review. The Iteration Assessment for the previous iteration, and the Issues List are again examined to make sure any residual issues are understood and it will be acceptable to the stakeholders to carry them forward. If any product was delivered to the customer for operational use in the current phase, the state of deployment should be examined to ensure that any required installation, training and transition activities have progressed acceptably.

If the phase end is also the end of the current contract (with the intent to re-contract for the next phase), the Project Manager will settle the project's finances, making sure all payments have been received and all suppliers and subcontractors paid. Organizational policy or other regulatory requirement may also require a more formal audit process at contract termination, covering the project's finances, budgeting process, and assets.

The Project Manager produces a Status Assessment that captures the results of the phase post-mortem review and the configuration audits, in preparation for the Lifecycle Milestone Review.

Distribute Artifacts to Stakeholders To top of page

Some time before the Lifecycle Milestone Review is to scheduled to be held, the Project Manager provides all stakeholders with copies of the artifacts which are to be considered at the Lifecycle Milestone Review. In a very formal contractual environment, the delivery of artifacts may well be contractually required to occur some weeks before the review. However, the Rational Unified Process recommends that the stakeholders be involved and engaged in the project to such a degree (in joint technical and management reviews, for example) that these deliveries should not be controversial; the stakeholders would already be familiar with the delivered material. They will have visibility of the evolution of the artifacts through the project's iterations. Even so, given the formal nature of these deliveries, the Deployment discipline will ensure that proper regard is given to packaging, labeling, installation, transition, and so on.

Artifacts Required

Complete Lifecycle Milestone Review Action Items To top of page

There may be some remaining actions following the Lifecycle Milestone Review, and sanction to begin the next phase may be conditional upon these. The Project Manager initiates work to resolve these items.

Copyright  © 1987 - 2001 Rational Software Corporation


Display Rational Unified Process using frames

Rational Unified Process