Table Plan Data Items
Data Item |
Description |
Project goals and constraints |
Targets and limits set by the project, team, or manager for example
|
Resources |
Available resources for mitigation. In order to develop effective action plans; planners need to know the limits of the available resources for mitigating and watching risks. |
Master list of risks |
A list of all risks that have been identified and the priority ranking of the top N risks. The top N designation helps planners decide how much effort to put into planning a particular risk or set of risks and the scope of resources that should be used for mitigation. |
Risk Information Sheet before Plan |
Information associated with each risk. Before planning this includes the statement of risk; supporting context; and values for impact, probability, timeframe, class, and rank. This could be all of the risks or a small subset assigned to the planners. |
Classification |
An organization of the risks according to their classification. Classification shows the relationships among risks and helps identify risks, which could be mitigated as a set. For example, classification could show which risks impact the system's user interface, which need to be mitigated as a set. |
Action Plan |
A description of what action is to be taken to deal with the risk(s). Risk action plans can be one of four types:
|
Risk Information Sheet After Plan |
Information associated with each risk, updated to include the approach to be taken for that risk (e.g., research, watch, accept, or mitigate). |