Task |
Description |
Duration in Work Days |
Dependent Upon |
|
|
|
|
T1 |
Concept document |
5 days |
None |
T2 |
Project Plan |
15 days |
T1 |
T3 |
Project Schedule |
10 days |
T1 |
T4 |
Requirements Analysis |
8 days |
T1 |
T5 |
Requirements Definition |
15 days |
T1 |
T6 |
System Specification |
8 days |
T1 |
T7 |
Requirements Validation |
10 days |
T4, T5, T6 |
T8 |
Architectural Design |
5 days |
T7 |
T9 |
Interface Design |
10 days |
T7 |
T10 |
Detailed Design |
9 days |
T7 |
T11 |
Coding |
20 days |
T8, T9, T10 |
T12 |
Unit Testing |
5 days |
T11 |
T13 |
Integration Testing |
10 days |
T11, T12 |
T14 |
System Testing |
15 days |
T13 |
T15 |
Acceptance Testing |
10 days |
T14 |
T16 |
User Manual |
10 days |
T8, T9, T10 |
Task |
Description |
Duration in Work Days |
Dependent Upon |
T1 |
Individual Component Testing |
5 days |
None |
T2 |
Input Processing and Monitoring Testing |
5 days |
T1 |
T3 |
Clock Module Testing |
1 day |
T1 |
T4 |
Timer Module Testing |
1 day |
T1 |
T5 |
Auto Cook Preset Module Testing |
1 day |
T1 |
T6 |
Auto Defrost Module Testing |
1 day |
T1 |
T7 |
Cooking Control Module Testing |
2 days |
T1 |
T8 |
Oven Control Module Testing |
1 day |
T1 |
T9 |
Timer Display Module Testing |
1 day |
T1 |
T10 |
Power Display Module Testing |
1 day |
T1 |
T11 |
Beeper Module Testing |
1 day |
T1 |
T12 |
Command Processing Sub-system Testing |
5 days |
T2 – T11 |
T13 |
Oven Control Sub-system Testing |
4 days |
T2 – T11 |
T14 |
Output Processing Sub-system Testing |
2 days |
T2 – T11 |
T15 |
Microwave Oven System Testing |
15 days |
T12 – T14 |
T16 |
Acceptance Testing |
10 days |
T15 |