Roles and Activities > Developer Role Set > Integrator > Create Baselines
Activity:
|
Purpose
|
|
Input Artifacts: | Resulting Artifacts: |
Frequency: On-going | |
Role: Integrator | |
Tool Mentor: |
Workflow Details: |
Good candidates for a baseline are the sets of files and directories under version control that are developed, integrated and released together. A baseline identifies one and only one version of a element.
Composite baselines are groupings of baselines delivered by teams working on separate subsystems of the overall project. In the event that multiple teams each deliver a baseline.
Part of the iterative development methodology is to constantly build an executable product. A baseline should be seen as the moving front of development which contains the necessary artifacts for subsequent development. So baselines should be created certainly at the end of each iteration.
Project baselining practices are followed in accordance with the
configuration identification, baselining and archiving step defined in Activity:
Establish CM Policies.
Rational Unified Process |